Work is still progressing on our overhaul on several fronts.
The loco is still at Leaky Finders in Devon. The new parts for the thermic syphons have arrived from Buckfastleigh, and they look good. The damaged sides of the inner firebox have been removed, in preparation for their replacement. The new boiler tubes are being prepared for insertion into the barrel, which we hope to start very soon.
The tender and support coach are still at Stewarts Lane, and both are being worked on.
The leaf springs on the tender have been sent away for testing, which proved successful. They have been refitted, and just need adjusting. This is known as “weighing”. The tender is loaded with coal and water, and the load on each wheel is measured. If any of the wheels are not close enough to the designed weight, the tender is jacked up, and shims are added to, or removed from, the top of the axleboxes. This is repeated until we are happy with the result. The tender is also being prepared for a full repaint.
We have also been working on our support coach. We have had a new toilet retention tank manufactured, and are in the process of fitting it.