To mark the eightieth anniversary of Victory in Europe Day, we had some extra embellishments to Clan Line’s appearance for this trip.

Because of the recent dry weather, the Network Rail fire risk was declared to be amber. This meant that we had a Class 67 diesel between Clan Line and our support coach. Our engine was allowed to do most of the work, but assistance was to be given where the loco would have had to work particularly hard. This happened, on the outward trip, on the climb to Shortlands after a signal check, the climb from Bromley South to Bickley, and after Selling station on the climb to the tunnel. On the return, it was on the climb from Tonbridge to Sevenoaks.

We left London Victoria almost on time, and arrived at Dover Priory, where we took water, only a minute late.
We left Dover almost on time, but were nine minutes early at Tonbridge. We were due to have a nine minute pathing allowance at Petts Wood Junction, but we were given the road, and were twenty two minutes early at Bickley Junction. We were held here for ten minutes, but another train behind us needed to get past and into Victoria. Therefore, we were diverted via the Catford Loop, which we can now take after the easement of a bridge prohibition. We finally got back to Victoria a couple of minutes late.