We are still awaiting the delivery of the pieces of boiler plate for the repairs to our thermic syphons. This wait is quite understandable. There is a lot of work involved in making the formers, which will be used to press the steel into the complicated shapes required. Our suppliers, unsurprisingly, don’t have skilled people like this waiting around just in case somebody wants some work done. They already have a full order book, and we just have to wait our turn.

We were due to replace all our smoke tubes and superheater elements this year, as part of the process of extending our seven-year boiler ticket to ten years. We had already decided to also replace the flue tubes at the same time. In preparation for this, all the old elements and tubes have been removed, and the new ones are already on site in Devon. This has all been done whilst we await the new pieces for the thermic syphons.

Over the last year or two, we have been having occasional leaking stays in the firebox. As we have the time at the moment, and the loco is in a boiler shop, we are also replacing a lot of stays as a precaution. The number affected could be between three and four hundred. So far, we have removed a lot of the cladding round the firebox to give us access to the outer ends of the stays. We have also removed the cab for the same reason. This is a non-trivial task, made even worse by all the electrical cabling that runs from the footplate. We have made a good start on grinding off the inner ends of these stays so that they can be drilled out.