Progress On The Boiler Repairs

New lower parts for the thermic syphons

Our specialist contractors have made more progress on the repairs to the thermic syphons. They have been working very hard to get Clan Line back out on the mainline. For most of September, they have worked seven days a week, often until quite late in the evening. Because of this, we now have the new parts to the fireman’s side thermic syphon tack-welded in place.

Tack-welding the new pieces in place
Thermic syphon repair tack-welded in place

This is not an easy job. The boiler is still on the frames, so all the tools and equipment has to go through the firehole door. Getting the new parts to fit is not straightforward. It involves a lot of cutting away of metal, and each cut has to be well considered, and small. If too much is removed, we will have to get new replacement pieces, and start all over again. After each cut, we have to wait for the piece to cool down slowly before it can be handled. Cooling it down quickly would induce stress in the metal.

Trial fitting one of the new pieces

During this process, we have discovered that our two thermic syphons are not the same, and neither of them is exactly to the drawing. This adds to the complexity of cutting the new pieces to fit. At times, we have had to use a lot of heat and pressure to modify the new parts to fit the old.

Heating and bending one of the new pieces

We have also discovered that the metal in some areas of the existing syphons is not as good as it could be. This was most probably caused during previous repairs in BR days.

This is all making the repairs take longer than we would have hoped.